Chemical industry

Scope of delivery and services:

  • Migration of the visualisation and operating components from PCS7 V7.0 to V8.2
  • Replacement of two CPU 417-4H controller pairs with CPU 410-5H
  • Production, supply and installation of two new server cabinets
  • Implementation of system changes as per customer specifications
  • Implementation of the automation security concept from Stadler + Schaaf
  • Setup of the web and BDIS server
  • Updating of existing documentation
  • Support operations after project completion with on-call service provided by Stadler + Schaaf

Special features:

  • Tight schedule for switching over to the new system during the removal of the old system as downstream plants continued to operate
  • Application whitelisting with centralised rights management
  • Implementation of a firewall to separate the quarantined network according to customer guidelines
  • All necessary services from cabinet assembly and installation, cabling and migration of the system, through to final commissioning were performed by Stadler + Schaaf