Pharmaceutical Industry

Scope of delivery and services:

  • Detail engineering for approx. 2,600 measurement and control devices incl. hosting the EI&C database
  • Supply and incoming goods inspection of more than 800 measurement and control devices
  • Detail engineering and supply of control systems, remote IO systems and solenoid valve islands
  • In-house production of all planned cabinets
  • In-house site setup and warehouse management
  • Installation and cabling, pneumatic air supply for all supplied components and measurement and control equipment in the clean room
  • Upgrading cable paths with stainless steel ducting
  • Installation Qualification (IQ) and OQ support

Special features:

  • GMP compliant completion throughout all stages of the project
  • Project duration of 16 months with approx. 4,700 engineering hours, 7,000 cabinet production hours and 27,000 assembly and commissioning hours
  • ProfiNet as the networking technology